RAID log

Everything that can move the date.

Risks, assumptions, issues, dependencies. One list, every line with a name and a day.

A hand-drawn clipboard log with four lettered rows

One migration, logged

The log on Monday 1 Feb. The risks came out of the pre-mortem at kickoff, 13 Jan.

The project
Move card processing from Ledgerline to Northpay. Cutover Sat 6 Mar, 02:00. Priya leads.

Risks

Might happen, with the date that settles it.

  • R1

    Ledgerline’s saved-card export arrives late, so 41,000 customers re-enter their cards.

    Odds / hit
    Medium / high
    Trigger
    No test export by Sat 6 Feb
    Owner
    Dana
    Status
    Watching.
  • R2

    The Ledgerline contract auto-renews for a year because notice goes out late.

    Odds / hit
    Medium / high
    Trigger
    Signed notice not sent by Sat 30 Jan
    Owner
    Marco
    Status
    Triggered 30 Jan. Now I1.
  • R3

    The rollback rehearsal fails, so we cut over with no way back.

    Odds / hit
    Low / high
    Trigger
    Rehearsal not clean by Sat 20 Feb
    Owner
    Priya
    Status
    Watching.

The day R2 became I1

The trigger date passed with the notice unsigned. Marco closed the risk and opened an issue.

Fri 29 Jan · risk

R2. The notice might go out late.

Settles on 30 Jan. Until then, Marco watches.

Sat 30 Jan · issue

I1. The notice is unsigned.

Hard deadline Mon 1 Feb. It is also why Monday’s status goes red.

Believed, or owed?

Assumption · A2

Refunds keep working on Ledgerline.

Nobody promised it; Marco believes it. It needs a check date: 10 Feb.

Dependency · D1

The firewall rule.

Sam promised it. It needs his name, not “platform”, and his date: 12 Feb.

Can you find out yourself? Assumption. Must you wait for someone? Dependency.

One row

Same fields for all four letters.

Log row
ID
R, A, I or D, plus a number
What
[one sentence; a risk says what might happen]
Owner
[one person on your side]
Date
[trigger, check by, resolve by, or due]
Odds / hit
[low, medium, high], risks only
Owed by
[their name, their team], dependencies only
Status
[what happened last, with its date]

Read it every Monday. Any date behind you means the row changes: closed, or a new letter.

A row without a name and a date is not a log entry. It is a worry with a number.